Phase II – Week 10

Phase II – Week 10

Week ten brings continued progress on window and door installation. The former fire exits from second and third floor OA have been restored back to windows as they were originally. Additionally, the new french doors into the living room have been installed:

Construction 2013-02-23 005

Construction 2013-02-23 006

Construction 2013-02-23 091

Plumbing for the new kitchen is coming along well, with floor drains and fixture rough-ins being plumbed:

Construction 2013-02-23 018

Construction 2013-02-23 047

Framing is beginning on second floor, with the layout being very similar to what’s already completed on third:

Construction 2013-02-23 056

Construction 2013-02-23 055

The electricians are still hard at work, and have started in the pledge wing now that the ceiling framing has been installed:

Construction 2013-02-23 068

Construction 2013-02-23 075