Phase II – Week 34
Week 34 is here, and we’re really getting down to the details before move-in. This last week was a lot of punchlist items. First up, the back lot is striped so you’ll know exactly how much your neighbor is infringing …
Week 34 is here, and we’re really getting down to the details before move-in. This last week was a lot of punchlist items. First up, the back lot is striped so you’ll know exactly how much your neighbor is infringing …
We’re really winding down construction here in the final weeks, but that means there’s a lot of finish details all coming together at the same time. First up is our new LED light for the flagpole. I haven’t seen it …
We’re coming down to the final weeks of our renovation, and there’s a lot of details coming together. One curveball was courtesy of Black Hills Energy, who installed a new gas line and moved our meter outside as part of …
A special thanks to brother Drew Stange for taking care of the construction update pictures while I was out of town. Week 31 brings a lot of finished lighting as the electricians wrap up, starting with new outdoor fixtures by …
Week 30 finally brings a moment a lot of people have been waiting for – the gravel is gone, we have a paved back parking lot: Our new door access controls are going in, which will be much improved over …
Week 29 starts off with progress on the last major concrete pour – the backlot. It’ll sure be nice not to be parking on gravel anymore. Prep is underway and forming should start right away this week: The sidewalk and …
A lot of concrete has been poured outside, but there’s still quite a bit more to go. The new basketball court is in, and the stairs have been formed up. After that they’ll move on to the rear sidewalks and …
Since it’s Friday afternoon, here’s a sneak peek behind the scenes at how this project is kept moving. Every other Friday afternoon there is a site visit meeting with the owners, architects, and contractors to discuss changes, problems, items noticed …