Phase II – Week 3

Week three begins with installation of electrical conduit in the back lot to provide new electrical service:
The old boiler system is also in process of begin removed, with liberal use of the cutting torch to create manageable pieces:
Inside, all the fixtures from the kitchen have been removed and stored temporarily in the dining room:
In the pledge wing, removal of the asbestos ceiling material continues:
And in the old wing, stripping of rooms continues, with third floor ahead of second floor: