Phase I – Week 7

Phase I – Week 7

Week seven and Phase I is wrapping up. The foundation work is finished and has been backfilled:

IMG_0349

IMG_0351

IMG_0352

In the former crawl space, plumbing is going in so the new concrete slab can be poured, which should be the last thing needed to finish up:

IMG_0361

IMG_0362