Phase II – Week 12

Phase II – Week 12

Week 12 brings a bit of rain, but also more progress. Outside, demolition has begun on the existing basketball court and retaining wall:

Construction 2013-03-09 004

The fire escape will be rotating and moving over to meet up with the new exit locations. The new footings are starting to be prepped and the new door frames are in also:

Construction 2013-03-09 006

Construction 2013-03-09 009

In the basement, part of the floor has been removed to smooth the transition out, and the new steel for the chapter room opening is being prepped:

Construction 2013-03-09 026

Construction 2013-03-09 034

Upstairs, the plumbers have moved onto the second floor bathroom:

Construction 2013-03-09 046

Construction 2013-03-09 044

In the pledge wing, the partition walls to split the rooms into sleeping/living spaces are being installed:

Construction 2013-03-09 051

Finally, up on third floor the arrival of drywall means as soon as the fire sprinklers are roughed-in, the ceilings and walls will start taking shape:

Construction 2013-03-09 062

Construction 2013-03-09 065