Phase II – Week 21

Phase II – Week 21

Week 21 begins outside, where you can see the steel workers have been busy building the platforms to connect the relocated fire stair to the new fire exits:

Construction 2013-05-11 006

Additionally, the forms are coming off the new retaining wall for the basketball court:

Construction 2013-05-11 007

In the kitchen, the new range hood has arrived and is being prepped to be installed this week:

Construction 2013-05-11 024

Construction 2013-05-11 027

Up on third floor, the first coat of paint is on the walls:

Construction 2013-05-11 052

Construction 2013-05-11 054

In the third floor bathroom, the tile has been grouted, which means the tile setters should be moving onto a new area soon (my bet is third floor laundry room, but we’ll see):

Construction 2013-05-11 057

Construction 2013-05-11 058

Up on the roof the mechanical contractor has been hard at work un-boxing and installing all of the new air conditioners:

Construction 2013-05-11 061

Construction 2013-05-11 065

Finally, down in the basement the framers and electricians have begun on the basement bathroom, which will be a huge transformation from the old boiler room:

Construction 2013-05-11 092

Construction 2013-05-11 091

4 Comments on “Phase II – Week 21

  1. Is anything being done to the chapter room or the room that is just off the chapter room, if you know what I mean.

Leave a Reply

Your email address will not be published. Required fields are marked *

*