Phase II – Week 22

Phase II – Week 22

Week 22 brings significant changes outside, especially to the front of the house. The existing walkway and stairs have been removed, which means we’re using the back door until the new concrete is poured:

Construction 2013-05-18 002

The basketball court is also being prepared for new concrete after additional earth is removed to bring the elevation down to be even with the side door:

Construction 2013-05-18 017

Inside, the new kitchen hood has been hung and vented:

Construction 2013-05-18 028

Construction 2013-05-18 031

Wall tile has been finished in the laundry rooms on second and third floors:

Construction 2013-05-18 066

Construction 2013-05-18 082

Up on third, the windows have started to be trimmed out, with the solid-surface stools being fitted:

Construction 2013-05-18 076

Also on third, the bathroom fixtures have arrived and are being installed:

Construction 2013-05-18 079

Construction 2013-05-18 080

Construction 2013-05-18 081

On the rear of the house, a couple windows had been held back from being installed to move materials in and out, but those are now finished:

Construction 2013-05-18 085