Phase II – Week 23

Week 23 brought a lot of rain, so it seems apt to see progress on the new storm-water system for the basketball court:
In the kitchen, the new exhaust hood for the dishwasher has been hung:
Around the corner in the men’s restroom, the accessible shower has at last made it’s way into it’s (almost) final position:
The tile-setters and painters have moved onto the second floor now:
Up on third, staining has begun for the woodwork. The color is hard to see, but it’s a dark brown to match the first floor woodwork:
Furnaces are being unboxed and installed in the mechanical closets throughout the house:
Continuing the mechanical trend, these massive water heaters are also being wrestled into place:
And finally, the new electrical service has been mounted and piped and the electricians are coordinating with LES to get the new service turned on soon: