Phase II – Week 16

Phase II – Week 16

Week 16 starts with an exciting milestone: drywall work has begun on third floor. This marks the end of the rough work and the beginning of finish work, and it helps to get a much better sense of how the layout feels.

Construction 2013-04-07 013

Construction 2013-04-07 024

Cement board is also going up the bathrooms in anticipation of tile work.

Construction 2013-04-07 015

Construction 2013-04-07 017

Framing is proceeding in the basement, which will be the last framing work needed.

Construction 2013-04-07 030

Construction 2013-04-07 038

Additionally, all of the holes in the floor for new plumbing have been patched.

Construction 2013-04-07 036

Construction 2013-04-07 047

Outside, matching replacement brick has arrived so the masons are beginning to patch in all the openings that have been modified such as the new fire escape doors on second and third floors.

Construction 2013-04-07 057

Construction 2013-04-07 056

In the basketball court, the foots for the relocated fire escape stair and the new retaining wall have been poured.

Construction 2013-04-07 053

Construction 2013-04-07 062

Finally, we received some samples of the furniture we’re planning to purchase and we’ve been evaluating them with some of the students’ help.